Applications75 registered
Delivered10 on time
Ran late4median 87 months
Rejected or revoked2applications
SAI GOLDEN ORCHIDS PHASE-6Gudibanda · Registration rejected · registered — SAI GOLDEN ORCHIDS PHASE 6Gudibanda · Registration rejected · registered — AASTHA PROPERTIES PHASE 6Gudibanda · Completed · registered Mar 2020 Due Nov 2021 AASTHA PROPERTIES PHASE 2Gudibanda · Overdue · registered Aug 2019 Due Dec 2020 Aastha propertiesGudibanda · Overdue · registered Mar 2019 Due Dec 2019 SAI GOLDEN ORCHIDS PHASE- 2Gudibanda · Overdue · registered Jan 2019 Due Mar 2018 SAI GOLDEN ORCHIDSGudibanda · Overdue · registered May 2018 Due Feb 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.