Astha Developers
Projects in Junagadh, Daskroi, Gandhinagar
Applications33 registered
Delivered10 on time
Ran late2median 48 months
Rejected or revoked0applications
TULSIVANJunagadh · Under construction · registered Feb 2023 Due Dec 2026 ASTHA VIHAR (Block A+D)Daskroi · Overdue · registered Feb 2018 Due Jul 2019 Bansari EleganceGandhinagar · Completion filed · registered Dec 2017 Due Dec 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.