Bharath Builders and Developers
Projects in Shivamogga, Chitradurga
Applications54 registered
Delivered40 on time
Ran late4median 28 months
Rejected or revoked1applications
Lake View ResidencyShivamogga · Completion filed · registered Mar 2025 Due Apr 2025 PREMIER LAYOUT PHASE 2Chitradurga · Registration rejected · registered — PREMIER LAYOUT PHASE 1Chitradurga · Completion filed · registered Nov 2021 Due Mar 2022 TARALABALU NAGAR PHASE 3Shivamogga · Completion filed · registered Oct 2019 Due Dec 2020 Taralabalu NagarShivamogga · Completed · OC received · registered Oct 2018 Due Mar 2018
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.