Coastal Karnataka Developers
Projects in Dakshina Kannada, Mangalore
Applications22 registered
Delivered20 on time
Ran late2median 8 months
Rejected or revoked0applications
Evanna HomesDakshina Kannada · Completion filed · registered Nov 2017 Due Mar 2018 NandagokulMangalore · Completion filed · registered Oct 2017 Due Jun 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.