Deepa House Building Co operative Society Ltd
Projects in MYSORE
Applications44 registered
Delivered20 on time
Ran late4median 34 months
Rejected or revoked0applications
NARAYANA GURU NAGARA Project 4MYSORE · Completion filed · registered Jan 2022 Due Sep 2023 NARAYANA GURU NAGARA- Project 3MYSORE · Overdue · registered Dec 2021 Due Sep 2023 NARAYANA GURU NAGARA- PROJECT 2MYSORE · Overdue · registered Dec 2021 Due Jun 2023 NARAYANA GURU NAGARAMYSORE · Completion filed · registered Mar 2021 Due Mar 2023
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.