EXPERION DEVELOPERS PVT. LTD.
CIN U70109DL2006FTC151343 · Projects in Plot No. Gh3, Sector 48, Guru Gram, Plot No. Gh-1 , Sector 42, Gu Rugram, Sector 112, Sector 108, Sector 108, Gurugram
Applications1616 registered
Delivered104 on time
Ran late9median 26 months
Rejected or revoked0applications
THE TRILLIONPlot No. Gh3, Sector 48, Guru Gram · Under construction · registered Feb 2025 Due Dec 2032 ONE42 GOLF COURSE ROADPlot No. Gh-1 , Sector 42, Gu Rugram · Under construction · registered Dec 2024 Due Dec 2034 WINDCHANTS PHASE CSector 112 · Under construction · registered Oct 2024 Due Mar 2030 WESTERLIES PHASE-2Sector 108 · Completed · OC received · registered Feb 2023 Due Sep 2024 HUB 108Sector 108, Gurugram · Overdue · registered Oct 2022 Due May 2024 WESTERLIES PHASE 1Sector 108 · Completed · OC received · registered Jul 2022 Due Sep 2024 WESTERLIESSector 108 · Completed · OC received · registered Nov 2021 Due Sep 2024 ZEPHYR AT THE WESTERLIESSector 108 · Overdue · registered Jun 2020 Due Jul 2024 WESTERLIESSector 108 · Completed · OC received · registered Nov 2019 Due Jan 2024 HEARTSONG PHASE 6Sector 108 · Completed · OC received · registered Oct 2019 Due May 2020 THE HEARTSONGSector 108 · Completed · OC received · registered Oct 2017 Due Oct 2018 THE HEARTSONG PHASE-5,2 NO. NURSERY SCHOOLVillage Dharampur,Sector-108 · Completed · OC received · registered Aug 2017 Due Aug 2020 WINDCHANTS PHASE -4,NURSERY SCHOOL SITEVillage Choma,Sector-112,Guru Gram · Overdue · registered Aug 2017 Due Aug 2020 RESIDENTIAL PLOTTED COLONY (WESTERLIES)Sector 108 · Completed · OC received · registered Aug 2017 Due Aug 2020 WINDCHANTS PHASE 3Sector 112, Choma · Completed · OC received · registered Aug 2017 Due Aug 2020 WINDCHANTS PHASE-2 ( T2, T3. S3 AND S4)Sector-112 · Completed · OC received · registered Aug 2017 Due Aug 2018
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.