Horizon Properties
Projects in Mangalore, Dakshina Kannada
Applications22 registered
Delivered10 on time
Ran late2median 26 months
Rejected or revoked0applications
Oriole HorizonMangalore · Completion filed · registered Mar 2020 Due Dec 2019 Horizon Greens and PlanetDakshina Kannada · Overdue · registered Mar 2020 Due Feb 2023
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.