Inesa Ventures LLP
Projects in Bengaluru East
Applications22 registered
Delivered00 on time
Ran late2median 16 months
Rejected or revoked0applications
DNR Arista Phase 2Bengaluru East · Overdue · registered Mar 2024 Due Jul 2026 DNR Arista Phase 1Bengaluru East · Overdue · registered Apr 2023 Due Dec 2024
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.