JOYVILLE SHAPOORJI HOUSING PVT LTD
CIN U70109MH2007PTC166942 · Projects in Kherki Majra, Sector 102, Gur Ugram, Village - Kherki,Majra Hadust - 52, Sec 102, Sector-102, Village-Kherki Majra, Sector- 102, Tehsil-Gurugram, District-Gurugram, Village-Kherki Majra, Sector- 102, Tehsil- Gurugram, District-Gurugram
Applications66 registered
Delivered64 on time
Ran late2median 0 months
Rejected or revoked0applications
JOYVILLE GURUGRAM PHASE VIKherki Majra, Sector 102, Gur Ugram · Completed · OC received · registered Jan 2021 Due Jul 2025 JOYVILLE GURUGRAM VVillage - Kherki,Majra Hadust - 52, Sec 102 · Completed · OC received · registered Sep 2019 Due Dec 2024 JOYVILLE GURUGRAM PHASE IIISector-102 · Completed · OC received · registered May 2019 Due Apr 2024 JOYVILLE GURUGRAM PHASE IVSector-102 · Completed · OC received · registered May 2019 Due Dec 2024 JOYVILLE GURUGRAM-IVillage-Kherki Majra, Sector- 102, Tehsil-Gurugram, District-Gurugram · Completed · OC received · registered Nov 2018 Due Mar 2023 JOYVILLE GURUGRAM-IIVillage-Kherki Majra, Sector- 102, Tehsil- Gurugram, District-Gurugram · Completed · OC received · registered Nov 2018 Due Sep 2023
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.