KARNAVATI BUILDERS
Projects in Gandhinagar, Ahmedabad City
Applications77 registered
Delivered73 on time
Ran late4median 7 months
Rejected or revoked0applications
KARNAVATI VIVANTA LIVING BLOCK FGandhinagar · Completion filed · registered Apr 2023 Due Dec 2026 KARNAVATI INFINITY LIVING BLOCK EAhmedabad City · Completion filed · registered Jan 2023 Due Dec 2026 KARNAVATI AVENUEGandhinagar · Completion filed · registered May 2021 Due Oct 2023 KARNAVATI INFINITY LIVINGGandhinagar · Completion filed · registered May 2020 Due Dec 2024 KARNAVATI VIVANTA LIVINGGandhinagar · Completion filed · registered Jun 2019 Due Jun 2023 KARNAVATI GOKULDHAMAhmedabad City · Completion filed · registered May 2018 Due May 2021 KARNAVATI PREMIER LIVINGAhmedabad City · Completion filed · registered Oct 2017 Due Oct 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.