KESHAVPRIYA CORP PRIVATE LIMITED
Projects in Ahmedabad City
Applications55 registered
Delivered52 on time
Ran late3median 8 months
Rejected or revoked0applications
NARODA SMART CITY-3Ahmedabad City · Completion filed · registered Jul 2018 Due Jun 2020 NARODA SMART CITY-2Ahmedabad City · Completion filed · registered May 2018 Due Aug 2018 Sahaj GreensAhmedabad City · Completion filed · registered Mar 2018 Due Mar 2019 NARODA BUSINESS HUBAhmedabad City · Completion filed · registered Mar 2018 Due Dec 2020 NARODA SMART CITYAhmedabad City · Completion filed · registered Mar 2018 Due Dec 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.