KG CONSTRUCTIONS
Projects in Lucknow
Applications33 registered
Delivered00 on time
Ran late0of those due
Rejected or revoked0applications
GOLF VISTA TOWER A2 & A3Lucknow · Past completion date · registered Aug 2017 Due Jun 2022 CELEBRITY GREENS TOWER L & MLucknow · Past completion date · registered Aug 2017 Due Dec 2019 CELEBRITY MEADOWS TOWER NLucknow · Past completion date · registered Aug 2017 Due Dec 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.