KINFRATECH
Projects in Udupi
Applications77 registered
Delivered75 on time
Ran late2median 0 months
Rejected or revoked0applications
DENDOOR COMMERCIAL CENTREUdupi · Completed · OC received · registered Oct 2024 Due Dec 2027 KINFRATECH PRIMEUdupi · Completed · OC received · registered Oct 2022 Due Sep 2023 Kinfratech NandanaUdupi · Completion filed · registered Jul 2020 Due Jun 2021 Kinfratech Ballal NagarUdupi · Completion filed · registered Jun 2020 Due Jun 2021 Kinfratech VistaraUdupi · Completed · OC received · registered May 2018 Due Dec 2021 Kinfratech NavanagaraUdupi · Completion filed · registered Apr 2018 Due Nov 2019 Kinfratech VistaUdupi · Completion filed · registered Feb 2018 Due Dec 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.