MAHENDRA DEVELOPERS
Projects in MYSORE, Hunsur
Applications55 registered
Delivered00 on time
Ran late4median 43 months
Rejected or revoked0applications
PARIJATHA ENCLAVEMYSORE · Under construction · registered Dec 2025 Due Oct 2026 Airavatha EnclaveHunsur · Overdue · registered Mar 2025 Due Sep 2025 Samruddhi EnclaveMYSORE · Overdue · registered Sep 2023 Due Oct 2024 BHAGYALAXMI NAGARAMYSORE · Overdue · registered Jul 2019 Due Jul 2022 Mayuram EnclaveMYSORE · Overdue · registered May 2018 Due Aug 2021
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.