Maithri Developers
Projects in Bengaluru East, Hosakote
Applications33 registered
Delivered10 on time
Ran late2median 38 months
Rejected or revoked0applications
MAITHRI SPRINGWOODSBengaluru East · Under construction · registered Jul 2026 Due Jul 2031 Shilpitha Tech ParkHosakote · Completed · OC received · registered Aug 2021 Due May 2023 Shilpitha Royal OakHosakote · Overdue · registered Feb 2019 Due Jun 2021
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.