MUZAFFARNAGAR DEVELOPMENT AUTHORITY
Projects in Budhana, Muzaffarnagar
Applications44 registered
Delivered00 on time
Ran late0of those due
Rejected or revoked0applications
256 E.W.S HOUSES UNDER PMAY AT BUDHANABudhana · Past completion date · registered Jul 2019 Due Feb 2023 448 E.W.S HOUSES UNDER PMAY AT BHOPA ROAD BYEPASS CROSSINGMuzaffarnagar · Past completion date · registered Jul 2019 Due Feb 2023 256 E.W.S HOUSES UNDER PMAY AT BEGRAJPURMuzaffarnagar · Past completion date · registered Jul 2019 Due Feb 2023 224 E.W.S HOUSES UNDER PANDIT DEENDAYAL UPADHAYAY NAGAR MEERUT ROAD MUZAFFARNAGARMuzaffarnagar · Past completion date · registered May 2019 Due Apr 2022
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.