PANARE BUILDERS & DEVELOPERS
Projects in Belagavi
Applications33 registered
Delivered32 on time
Ran late1median 0 months
Rejected or revoked0applications
SHREE DEVAMALA RESIDENCYBelagavi · Completed · OC received · registered Jun 2023 Due Jul 2027 SHREE KRUPASINDHUBelagavi · Completed · OC received · registered Aug 2021 Due Mar 2026 SHREE SAI SRUSHTI (PHASE -2)Belagavi · Completion filed · registered Oct 2017 Due May 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.