PRATHAM PROPERTIES
Projects in Vadodara
Applications1010 registered
Delivered84 on time
Ran late4median 3 months
Rejected or revoked0applications
Pratham Bluets phase 8Vadodara · Under construction · registered Apr 2024 Due Apr 2028 Pratham Plaza Tower DVadodara · Completion filed · registered Oct 2023 Due Dec 2025 Pratham Bluets Phase 9Vadodara · Under construction · registered Sep 2023 Due Dec 2026 Pratham Bluets Phase-7Vadodara · Completion filed · registered Nov 2021 Due Jun 2025 Pratham Paradise Phase 02Vadodara · Completion filed · registered Nov 2021 Due Jun 2023 Pratham Bluets Phase-6Vadodara · Completion filed · registered Sep 2021 Due Jul 2024 Pratham Bluets Phase-5Vadodara · Completion filed · registered Sep 2021 Due Jul 2022 Pratham Meadows Phase 2Vadodara · Completion filed · registered Jul 2018 Due Mar 2021 Pratham IvyVadodara · Completion filed · registered Mar 2018 Due Dec 2020 Pratham Bluets Phase-4Vadodara · Completion filed · registered Mar 2018 Due Jun 2018
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.