Premier Properties
Projects in Kanakapura, Bengaluru South, Bengaluru East
Applications44 registered
Delivered20 on time
Ran late3median 26 months
Rejected or revoked0applications
PREMIER JEWELSKanakapura · Overdue · registered Nov 2023 Due Jul 2024 SLICE OF HEAVENBengaluru South · Overdue · registered Jul 2022 Due Apr 2024 Premier Inspira MaplewoodBengaluru East · Completed · OC received · registered Jun 2018 Due Feb 2022 Premier KrishnaBengaluru South · Completed · registered May 2018 Due Dec 2018
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.