PURAVANKARA LIMITED
Projects in Vandalur, Chennai
Applications55 registered
Delivered00 on time
Ran late0of those due
Rejected or revoked0applications
PROVIDENT BAYSCAPEVandalur · Under construction · registered Sep 2024 Due Aug 2028 Purva Windermere Phase-4AChennai · Under construction · registered Jan 2023 Due Dec 2027 Purva Windermere Phase-4BChennai · Under construction · registered Jan 2023 Due Dec 2028 Purva Windermere Phase-4CChennai · Under construction · registered Jan 2023 Due Dec 2029 Purva Somerset HouseChennai · Overdue · registered Jan 2019 Due Mar 2023
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.