PYRAMID INFRATECH PRIVATE LIMITED
CIN U45400HR2008PTC038509 · Projects in Village Begampur Khatola Sect Or 71, Village Bambad, Sector 22 & 3 3, Sector- 73, Sector- 70 A,, Village Badha, Sector-86
Applications1212 registered
Delivered83 on time
Ran late7median 10 months
Rejected or revoked0applications
ALBANVillage Begampur Khatola Sect Or 71 · Under construction · registered Mar 2024 Due May 2030 EMERALD ESTATEVillage Bambad, Sector 22 & 3 3 · Overdue · registered Oct 2023 Due Jun 2026 GRAND VISTASector- 73 · Completed · OC received · registered May 2022 Due Dec 2026 IMPERIAL ESTATESector- 70 A, · Completed · OC received · registered May 2022 Due Dec 2026 URBAN HOMES-II EXTENSIONVillage Badha, Sector-86 · Completed · OC received · registered Sep 2020 Due Nov 2023 PYRAMID PRIDESector-76 · Completed · OC received · registered May 2019 Due Feb 2024 PYRAMID HEIGHTSSector-85 · Part OC received · registered May 2019 Due Jun 2025 PYRAMID FUSION HOMESVillage Palra Sector 70a · Completed · OC received · registered Feb 2019 Due Aug 2024 PYRAMID ELITESector- 86, Manesar · Completed · OC received · registered Jan 2019 Due Jul 2024 URBAN 67-ASector-67-A, Gurugram, Haryan A · Completed · OC received · registered Nov 2017 Due Oct 2022 URBAN HOMESSector 70a · Completed · OC received · registered Oct 2017 Due Feb 2020 URBAN HOMES IISector 86 · Past completion date · registered Oct 2017 Due Feb 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.