RADICON INFRASTRUCTURE & HOUSING PVT LTD
Projects in Gautam Buddha Nagar
Applications33 registered
Delivered00 on time
Ran late0of those due
Rejected or revoked0applications
VEDANTAM PHASE 1 (TOWER E1, E2, D1, B2 & A)Gautam Buddha Nagar · Past completion date · registered Aug 2017 Due Mar 2018 VEDANTAM PHASE-2( TOWER B1, C2 & C1)Gautam Buddha Nagar · Past completion date · registered Aug 2017 Due Dec 2018 VEDANTAM PHASE-3(TOWER D2F & G)Gautam Buddha Nagar · Past completion date · registered Aug 2017 Due Dec 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.