RAJGREEN INFRALINK LLP
Projects in Surat City
Applications22 registered
Delivered10 on time
Ran late2median 21 months
Rejected or revoked0applications
VANILLA SKYSurat City · Overdue · registered Apr 2019 Due Sep 2025 THE BLUEBELLSurat City · Completion filed · registered Sep 2017 Due Mar 2021
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.