Applications33 registered
Delivered10 on time
Ran late2median 62 months
Rejected or revoked0applications
REDBRICKS PALM HILLS BLOCK B AND BLOCK CMangalore · Under construction · registered Feb 2020 Due Sep 2032 Redbrick Village Phase 3 WING BMangalore · Overdue · registered Jan 2018 Due Jun 2019 REDBRICKS PALM HILLS BLOCK AMangalore · Completion filed · registered Dec 2017 Due Jun 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.