ROSEBERRY ESTATE LLP
Projects in Gautam Buddha Nagar
Applications33 registered
Delivered00 on time
Ran late0of those due
Rejected or revoked0applications
GODREJ WOODS PHASE-3Gautam Buddha Nagar · Under construction · registered Jan 2022 Due Oct 2027 GODREJ WOODS PHASE IIGautam Buddha Nagar · Under construction · registered May 2021 Due Jan 2027 GODREJ WOODS PHASE-1Gautam Buddha Nagar · Past completion date · registered Feb 2021 Due Jul 2026
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.