S AND S BUILDERS AND DEVELOPERS
Projects in Hubballi, Anekal, Tumakuru, MYSORE, Bengaluru East
Applications66 registered
Delivered21 on time
Ran late5median 10 months
Rejected or revoked0applications
NEWLAND PARKHubballi · Overdue · registered Jul 2023 Due Dec 2025 S S BRINDAVANAMAnekal · Overdue · registered May 2023 Due Dec 2025 RAMESH LAYOUTTumakuru · Overdue · registered Apr 2022 Due Jun 2022 Sree Nagar Phase 1MYSORE · Completion filed · registered Nov 2019 Due Sep 2026 SS SNOWDROPBengaluru East · Overdue · registered Jul 2018 Due Mar 2021 TRILLIUM APARTMENTSAnekal · Completed · OC received · registered Mar 2018 Due Jan 2021
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.