S S REALTY
Projects in Mangalore
Applications77 registered
Delivered41 on time
Ran late5median 34 months
Rejected or revoked0applications
LANDMARK PRIMUSMangalore · Completed · OC received · registered Apr 2022 Due Jan 2025 LANDMARK LEXAMangalore · Completed · registered May 2018 Due Jul 2022 LANDMARK AYUSHMangalore · Overdue · registered May 2018 Due Jul 2022 LANDMARK PHOENIXMangalore · Overdue · registered Feb 2018 Due Jul 2022 LANDMARK GREEN COUNTYMangalore · Completed · OC received · registered Oct 2017 Due Mar 2021 LANDMARK GRAND CITYMangalore · Overdue · registered Oct 2017 Due Sep 2021 LANDMARK OXYGENMangalore · Completion filed · registered Oct 2017 Due Oct 2018
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.