SAI RENIIT PROJECTS PVT.LTD.
CIN U70100KA2013PTC072016 · Projects in Anekal
Applications76 registered
Delivered40 on time
Ran late5median 27 months
Rejected or revoked1applications
SAI METRO CITY 9TH PHASEAnekal · Under construction · registered Jan 2026 Due Nov 2026 SAI METROCITY 8TH PHASEAnekal · Overdue · registered Jan 2023 Due Jun 2025 SAI METRO CITY 7TH PHASEAnekal · Completion filed · registered Sep 2021 Due Dec 2021 Sai Metro city 5th phaseAnekal · Completion filed · registered Jun 2020 Due Jun 2023 SAI BLOSSOM WINDSAnekal · Registration rejected · registered — SAI METRO CITY PH 6Anekal · Completion filed · registered Jan 2019 Due Feb 2020 SAI PARADISE EXTENSIONAnekal · Completion filed · registered Dec 2018 Due Aug 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.