Applications66 registered
Delivered21 on time
Ran late4median 21 months
Rejected or revoked0applications
Vinayaka Garden city PlatinumMYSORE · Under construction · registered Jun 2026 Due Mar 2027 Heritage City IMYSORE · Overdue · registered Mar 2024 Due Dec 2024 SVG CityMYSORE · Overdue · registered Jan 2024 Due Mar 2024 HERITAGE CITY IIMYSORE · Overdue · registered Jan 2024 Due Dec 2024 Sathyanarayan Y.SMYSORE · Completion filed · registered Mar 2021 Due Apr 2021 HOME CROWN MANSIONMYSORE · Completed · OC received · registered Oct 2019 Due Oct 2021
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.