SHAILESHBHAIPRANLALGONAWALA
Projects in Surat City
Applications33 registered
Delivered30 on time
Ran late3median 5 months
Rejected or revoked0applications
SAI ENCLAVESurat City · Completion filed · registered Apr 2019 Due Dec 2023 SAI KG HEIGHTSSurat City · Completion filed · registered Mar 2018 Due Dec 2019 SAI MOHAN FLATSSurat City · Completion filed · registered Mar 2018 Due Jun 2022
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.