SHILP INFRASTRUCTURE
Projects in Ahmedabad City, Daskroi
Applications22 registered
Delivered20 on time
Ran late2median 21 months
Rejected or revoked0applications
SANSKAR ENCLAVEAhmedabad City · Completion filed · registered Oct 2021 Due May 2026 SHILP BUNGLOWDaskroi · Completion filed · registered May 2018 Due Dec 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.