SHIVAM DEVELOPERS
Projects in Ahmedabad City, Vadodara, Pardi, Daskroi, Rajkot
Applications4747 registered
Delivered3428 on time
Ran late11median 0 months
Rejected or revoked0applications
ATHARVA POSH VILLEAhmedabad City · Under construction · registered May 2025 Due Apr 2029 OM EXOTICAVadodara · Under construction · registered May 2025 Due Apr 2030 Royal PalacePardi · Under construction · registered May 2024 Due Apr 2028 BILIPATRADaskroi · Under construction · registered Nov 2023 Due Apr 2028 AARYA EUPHORIAVadodara · Under construction · registered Jun 2023 Due Apr 2028 DWARIKA PRIDERajkot · Completion filed · registered Sep 2022 Due Aug 2023 Shivay AtlantisGandhinagar · Completion filed · registered Sep 2022 Due Mar 2027 ALAYA BELMONTEAhmedabad City · Completion filed · registered Jul 2022 Due Jun 2026 PUSHPAM HEIGHTSAhmedabad City · Completion filed · registered May 2022 Due Mar 2027 SHIVAM PALACEChorasi · Completion filed · registered Feb 2022 Due Dec 2026 Shivaay LandmarkVadodara · Under construction · registered Dec 2021 Due Jul 2027 SHIVAM BUNGLOWSAhmedabad City · Completion filed · registered Dec 2021 Due Dec 2024 SHIVAM AVENUE-IIJamnagar · Completion filed · registered Oct 2021 Due Mar 2026 SHIVAM SQUAREJamnagar · Completion filed · registered Oct 2021 Due Mar 2024 ISHA BUNGALOWSVadodara · Under construction · registered Jul 2021 Due Apr 2027 Fortune HeightsJunagadh · Completion filed · registered Jul 2021 Due Dec 2024 Atharva LandmarkAhmedabad City · Completion filed · registered May 2021 Due Dec 2024 Shubham ResicomVadodara · Completion filed · registered Mar 2021 Due Jun 2025 SHREENAND ATRIAAhmedabad City · Completion filed · registered Dec 2020 Due Dec 2025 DEEPAM SQUAREUmbergaon · Overdue · registered Jun 2020 Due Jun 2024 Shivam AvenueRajkot · Completion filed · registered May 2020 Due Jun 2021 SUMUKH TOWNSHIPValsad · Under construction · registered Mar 2020 Due Oct 2027 SHIVAM APPARTMENTAhmedabad City · Overdue · registered Mar 2020 Due Jun 2022 Siddhi HeritageRajkot · Completion filed · registered Jan 2020 Due Jun 2025 Shivam HeightsVadodara · Completion filed · registered Aug 2019 Due Jun 2023 NIRVANA BUSINESS HUBVadodara · Completion filed · registered Apr 2019 Due Sep 2022 SAFFRON LUXURIAKamrej · Completion filed · registered Apr 2019 Due Sep 2024 SILK ROUTERajkot · Completion filed · registered Mar 2019 Due Jun 2023 SHIVAM AVENUEJamnagar · Completion filed · registered Mar 2019 Due Jun 2024 SOLITAIRE SQUAREAhmedabad City · Completion filed · registered Feb 2019 Due Sep 2021 KRISHNA RESIDENCYPadra · Completion filed · registered Jan 2019 Due Mar 2020 ROYAL EDIFICEVadodara · Completion filed · registered Dec 2018 Due Jun 2023 PUSHPAK EXOTICAVaghodia · Overdue · registered Dec 2018 Due Jan 2022 SHIVAM COMPLEXGandevi · Completion filed · registered Dec 2018 Due Nov 2020 Sundaram VillaVadodara · Overdue · registered Dec 2018 Due Dec 2019 AARYA ENCLAVEVadodara · Completion filed · registered Nov 2018 Due Jun 2020 BILIPATRARajkot · Completion filed · registered Oct 2018 Due Jun 2019 PRAKRUTI GREENSVadodara · Completion filed · registered Oct 2018 Due Mar 2021 TIRUPATI HEIGHTSAhmedabad City · Completion filed · registered Sep 2018 Due Sep 2024 SHIVAM FLATSRajkot · Completion filed · registered Sep 2018 Due May 2019 PEARL 79Ahmedabad City · Completion filed · registered Sep 2018 Due Dec 2021 SHIVAM SANIDHYAAhmedabad City · Completion filed · registered Jul 2018 Due Dec 2024 AARYA ELITEPadra · Completion filed · registered Jul 2018 Due Dec 2019 Pushkar Homes (Block D+E)Ahmedabad City · Completion filed · registered Mar 2018 Due Jun 2018 SHIV DRASHTI RESIDENCYChorasi · Overdue · registered Feb 2018 Due Oct 2023 SHIVAM GRACEAhmedabad City · Completion filed · registered Jan 2018 Due Sep 2018 Advait ResidencyAhmedabad City · Completion filed · registered Dec 2017 Due Sep 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.