SHREE RAJ GROUP
Projects in Modasa
Applications22 registered
Delivered22 on time
Ran late0median 0 months
Rejected or revoked0applications
paavancity phase 3Modasa · Completion filed · registered Apr 2019 Due Jun 2023 PAAVANCITY PHASE 2Modasa · Completion filed · registered Mar 2018 Due Dec 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.