SHREEJI PROCON
Projects in Ahmedabad City, Gandhinagar
Applications22 registered
Delivered21 on time
Ran late1median 6 months
Rejected or revoked0applications
SERENITY SQUAREAhmedabad City · Completion filed · registered Jul 2021 Due Mar 2025 TIRUPATI TIRTHGandhinagar · Completion filed · registered Oct 2020 Due Dec 2024
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.