SHRIYA PROPERTIES
Projects in Hubballi, Dharwad
Applications44 registered
Delivered33 on time
Ran late1median 0 months
Rejected or revoked0applications
SHRIYA LUMBINIHubballi · Completed · OC received · registered Aug 2021 Due Oct 2023 STELLARHubballi · Completed · OC received · registered Sep 2018 Due May 2022 SHRIYA LOTUSHubballi · Overdue · registered May 2018 Due Jan 2022 SHRIYA SOLITAIREDharwad · Completed · OC received · registered Oct 2017 Due Dec 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.