SHYAM DEVELOPERS
Projects in Ahmedabad City, Daskroi, Surat City, Bavla, Rajkot
Applications2121 registered
Delivered1715 on time
Ran late2median 0 months
Rejected or revoked0applications
Prestige SquareAhmedabad City · Under construction · registered Apr 2026 Due Mar 2029 SHYAM 95Daskroi · Under construction · registered Jan 2026 Due Apr 2029 BALRAJ HERITAGEDaskroi · Under construction · registered May 2025 Due Apr 2030 SHYAM 68Ahmedabad City · Under construction · registered Jan 2025 Due Apr 2027 SHYAM RESIDENCYSurat City · Completion filed · registered Apr 2023 Due Dec 2026 ALOK SKY CITYBavla · Completion filed · registered May 2022 Due Dec 2027 SHYAM SANIDHYARajkot · Completion filed · registered Apr 2022 Due Mar 2025 SHYAM PALACEJunagadh · Completion filed · registered Dec 2021 Due May 2025 SILVER PALACERajkot · Completion filed · registered Feb 2021 Due Dec 2022 Polaris CelestiaGandhinagar · Completion filed · registered Dec 2020 Due Dec 2025 ASOPALAV HEAVENRajkot · Completion filed · registered Jan 2020 Due Jun 2023 MADHAV RESIDENCYSurat City · Completion filed · registered May 2019 Due Jun 2025 SILICON PALM (BUILDING C, J+K)Surat City · Completion filed · registered Apr 2019 Due Jun 2025 SHYAM RESIDENCYSurat City · Completion filed · registered Apr 2019 Due Jun 2026 Shivalay ResidencyAhmedabad City · Completion filed · registered Dec 2018 Due Aug 2019 CORAL PRIDEVadodara · Completion filed · registered Nov 2018 Due Jun 2022 KALP INDUSTRIAL PARKAhmedabad City · Completion filed · registered Jul 2018 Due Dec 2022 Shyam VillaAhmedabad City · Completion filed · registered Jun 2018 Due Jun 2023 NAND EXOTICAVadodara · Completion filed · registered Jun 2018 Due Sep 2021 SHYAM RESIDENCYAhmedabad City · Completion filed · registered Jun 2018 Due Sep 2018 RADHEY HEIGHTSAhmedabad City · Completion filed · registered Oct 2017 Due Jun 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.