SNR Square Pvt Ltd
CIN U45201KA2014PTC074103 · Projects in Anekal, Bengaluru South
Applications55 registered
Delivered31 on time
Ran late4median 24 months
Rejected or revoked0applications
SNR SAFAAnekal · Overdue · registered Nov 2022 Due Feb 2025 SNR MAGNOLIA PARKAnekal · Completed · OC received · registered Nov 2020 Due Jul 2022 SNR MAYFAIRBengaluru South · Overdue · registered Jul 2019 Due Apr 2021 SNR Wind MillBengaluru South · Completion filed · registered Apr 2018 Due Mar 2020 SNR VerityAnekal · Completed · OC received · registered Dec 2017 Due Mar 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.