SR INFRA
Projects in Surat City
Applications22 registered
Delivered21 on time
Ran late1median 9 months
Rejected or revoked0applications
RUDRA PALACESurat City · Completion filed · registered Jun 2020 Due Jun 2024 RUDRA VILLASurat City · Completion filed · registered Mar 2019 Due Mar 2022
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.