SRI BALAJI BUILDERS
Projects in Bengaluru East, Anekal
Applications44 registered
Delivered11 on time
Ran late3median 6 months
Rejected or revoked0applications
SRI BALAJI VAIBHAVBengaluru East · Overdue · registered Feb 2025 Due Jun 2026 URBAN RETREATAnekal · Overdue · registered Mar 2024 Due Dec 2025 WHITE WOODSBengaluru East · Overdue · registered Apr 2021 Due Dec 2024 BALAJI MONARCHBengaluru East · Completed · OC received · registered May 2018 Due Dec 2020
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.