TATHYA INFRASPACE PRIVATE LIMITED
Projects in Daskroi
Applications88 registered
Delivered30 on time
Ran late7median 51 months
Rejected or revoked0applications
SHYAM VATIKA PHASE 1Daskroi · Under construction · registered Mar 2026 Due Dec 2030 ASHRAYA 10 (PHASE-1)Daskroi · Completion filed · registered Jan 2018 Due Dec 2020 ASHRAYA 10 (PHASE - 2)Daskroi · Completion filed · registered Jan 2018 Due Dec 2020 ASHRAYA 10 (PHASE - 3)Daskroi · Completion filed · registered Jan 2018 Due Jun 2021 ASHRAYA 10 (PHASE - 4)Daskroi · Overdue · registered Jan 2018 Due Jun 2022 SOMYA RESIDENCYDaskroi · Overdue · registered Jan 2018 Due Sep 2022 SOMYA RESIDENCYDaskroi · Overdue · registered Jan 2018 Due Sep 2022 SOMYA RESIDENCYDaskroi · Overdue · registered Jan 2018 Due Sep 2022
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.