TETRA GRAND CONSTRUCTIONS
Projects in Bengaluru North
Applications32 registered
Delivered00 on time
Ran late2median 48 months
Rejected or revoked1applications
TETRA GRAND GREEN ESSENCEBengaluru North · Overdue · registered Aug 2023 Due Dec 2025 TETRA GRAND'S GREEN ADMIRE A BLOCKBengaluru North · Registration rejected · registered — TETRA GRAND'S GREEN ADMIRE 'B' BLOCKBengaluru North · Overdue · registered Dec 2018 Due Jun 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.