Total Green Homes LLP
Projects in Devanahalli
Applications44 registered
Delivered20 on time
Ran late2median 26 months
Rejected or revoked0applications
Classic Bulwark Village Phase 4BDevanahalli · Overdue · registered Aug 2023 Due Dec 2024 CLASSIC CANAANDevanahalli · Overdue · registered Jul 2022 Due Mar 2024 Classic AmaraDevanahalli · Completed · registered Jan 2020 Due Dec 2021 Total Green HomesDevanahalli · Completed · registered Sep 2019 Due Apr 2022
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.