UH REALCON PRIVATE LIMITED
Projects in Ghaziabad
Applications44 registered
Delivered00 on time
Ran late0of those due
Rejected or revoked0applications
URBAN HOMES PHASE 1AGhaziabad · Past completion date · registered Jul 2017 Due Mar 2019 URBAN HOMES PHASE 1BGhaziabad · Past completion date · registered Jul 2017 Due Oct 2022 URBAN HOMES PHASE 1CGhaziabad · Past completion date · registered Jul 2017 Due Apr 2022 URBAN HOMES PHASE 1DGhaziabad · Past completion date · registered Jul 2017 Due Oct 2022
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.