VEER DEVELOPERS
Projects in Ahmedabad City, Rajkot, Gandhinagar
Applications44 registered
Delivered32 on time
Ran late2median 3 months
Rejected or revoked0applications
VERTIS ONEAhmedabad City · Completion filed · registered Mar 2021 Due Sep 2024 BOMBAY SUPER HEIGHT -3Rajkot · Completion filed · registered Feb 2020 Due Feb 2022 Mahavir Hills-2Gandhinagar · Overdue · registered May 2019 Due Sep 2019 VAIKUNTH DARSHANAhmedabad City · Completion filed · registered Sep 2017 Due Dec 2019
Open any project for its IQ Score and how late this builder's other projects ran.
Grouped by the promoter name on RERA, ignoring words like “Pvt Ltd”. Group companies that file under other names appear separately. Lateness is measured from each project’s original date, not counting the Covid-19 extension.